A sleek new build development located right in the heart of Liverpool City

This sleek new build development incorporates 449 units over three blocks, located right in the heart of Liverpool City. These stunning apartments will be delivered with a contemporary finish and are within easy reach of Liverpool’s vibrant city centre that boasts a diverse mix of bars, restaurants, theatres and shopping centres to suit everyone.

Great care and attention have been given to the outside spaces around the village to allow the most relaxing and pleasurable living experience. With a private courtyard, complete with lush greenery, Satin residence provides the most enjoyable space for you to wind down, including rooftop spaces and beautiful landscapes areas.

Every aspect of Satin Residence interiors has been meticulously considered to ensure the most delightful living experience. The kitchens, bathrooms, and living areas are designed to cater to your every need. They come furnished with a suite of modern design features, including high-quality surfaces, sleek fittings and top of the line fixtures. Satin Residence is not only beautiful to look at, it is also a place you would be proud to call Home.

Property Highlights

  • Studio - 2 Beds
  • 1 - 2 Baths
  • 30 - 65 sq.m
  • Gildart Street
    Liverpool. L3 8HA
  • Excellent Location
  • Great Transport Links
  • Contemporary Kitchens
  • Modern Bathroom Suites
  • Stylish Interiors
  • Private Courtyard
  • Rooftop Spaces
  • 7% Rental Yield
  • Yield Assured for 3 Years
  • 3 Years Free Lettings

May 2020

Unfortunately due to the March lockdown enforced by the UK Government it is unlikely that Fabric Village will be completed before 2021. The site manager is making weekly visits to expedite the construction process and trying to reduce any further delays. The man power and contractor allocations is also set to be increased to try and offset the current delay.

Construction Updates
95% of the retaining wall has now been completed as well as the party walls being fully completed. All the ground floor foundations are complete with bolt boxes cast in and the rib deck floor planks delivery has arrived.

October 2019

- Currently there are 33 operatives on site
- Base plates finished in readiness for steel
- Formwork removal to lift shaft base underway
- Stripping of formwork from bolt bases to steel columns underway
- Stripping of bolt base formwork against retaining wall underway
- Emergency works to support old retaining wall almost completed
- Repairs almost complete to the party wall

August 2019

- New guttering installed at adjacent party wall
- Masonry work complete
- Cladding & rails commenced last week to conclude party wall works
- Site strip initial phase continuing
- Main site clearance commenced, approximately 250 loads to be removed
- Concrete pouring for strip foundations ongoing
- Steel framework order placed
- Steel framework delivery and erection due end of August