Northgate Studios is a luxury, purpose built student property offering investors a NET yield of 8% per annum, assured for 5 years. Strategically located close to the university and the city centre, this is the perfect solution for students looking for independent living in a high quality and safe environment.

The development is 6-storeys with a total of 150 student studio apartments range in size from 20 sq meters – 36 sq meters. Each unit is designed to match the current market demand for high-specification accommodation, and includes: en-suite bathrooms, bespoke kitchens with contemporary appliances living, study and sleeping areas.

Additional facilities for students will include cycle storage, group study areas, vehicle drop off point, storage, laundry facilities, secure door opening systems and manned reception and is expected to be completed by August 2018.

Property Highlights

  • Studio
  • 1 Bath
  • 20 sq.m - 36 sq.m
  • Trafford Street
    Chester. CH1 3HP
  • Close to University
  • Walking Distance to City Centre
  • High Quality
  • Safe Environment
  • Bespoke Kitchens
  • Cycle Storage
  • Laundry Facilities
  • Manned Reception
  • Assured 8% NET Yield

February 2018

- Phase 1 metsec and Phase 2 steel frames are complete
- The roof is completed
- All windows on Phase 1 are installed. Window installation for Phase 2 ongoing
- The brick work is completed on Phase 1
- 12 brick work courses completed on Phase 2
- 1st fixings completed on Phases 1 and 2
- Plastering on floors 1-3 completed
- Mist coating commencing on 26th February
- Lift shaft completed from ground floor to 2nd floor. Currently progressing 3rd to 4th floor
- Tower crane comes down on 26th February
- Overall strong progress and meeting programme milestones

November 2017

- Phase 1 Metsec frame is erected
- Phase 2 steel frame is 60% complete
- All steel work due to be complete in next 2 weeks
- Roof lining is on
- All window frames are in
- Glass is due on site next week
- All the floor slabs are in
- All the bathroom pods for phase 1 have been delivered
- Phase 2 bathroom pods are due on 8th December
- The external brick work is up to first floor
- Boarding and electrical first fixing has commenced

August 2017

- Sub-structure is complete
- Slab is being formed
- First phase of steel work is well underway
- Off-site bathroom pods start arriving from next week

July 2017

- All the enabling works have been completed including the strip and demolition of the existing building
- The site has been levelled and the site set up and accommodation is now fully on site
- The foundations and steel frame work is now commencing

May 2017

- Site now demolished
- Beginning building the foundations in two weeks
- Steel structure to begin in the next six weeks

FX Illustration

£
Approx.

Disclaimer
Rates are updated every 24hrs

Stamp Duty

£
Approx.
Next steps
Speak to one of our expert consultants today

Our customers

Friendly and Pro-active

In my dealings with them I found Flambard Williams helpful, friendly and pro-active.

Mr D Jones
More than a sale

We dealt with Charleigh Cooper and I found her to be excellent and responsive to every question, query I have had. She has checked in with me on the progress through out and followed up with the developer and solicitors as requested which is over and above the service of a selling agent and better than expected.

Mrs R Shah
A very impressive company

I can’t really praise the service I’ve received highly enough. Personal, professional and very efficient. Charleigh has been with me the whole way and I can’t thank her enough. I would recommend this company to anyone!

Mr J Wild
Great service

Friendly, helpful and professional staff. Very pleased with my purchase.

Jessica
Good communication & regular feedback

I am pleased with my relationship with FW. Communication 4000 miles away and different time zone and weekend holidays was very effective and personal.

Mr Husain

As featured in