Manchester Mill | Flambard Williams

A striking Grade II former textile mill

Manchester Mill is a striking Grade II former textile mill located on the banks of the Rochdale Canal, to the north east of Manchester city centre. It’s bold six-storey red-brick façade and towering chimney has dominated the local skyline for over one and a half centuries.

Why Invest in Manchester Mill?

This former mill now offers luxurious apartments featuring exposed brick which have been created for professionals keen to benefit from easy access to the city centre for work and pleasure. From each apartment window, the Mill’s panoramic views across the city and surrounding suburbs can be fully appreciated. Manchester is currently apart of a £1billion regeneration project and also has the highest student population outside of London.

Manchester Mill Location

This development sits in the heart of the thriving East Manchester area of regeneration. Located within touching distance of the Mill, is the home of some of the largest concentration of major sporting venues in Europe. Within a short distance you can find Manchester United football stadium and also the Etihad Stadium the home of the Premier League Champions Manchester City.

Residents of Manchester Mill have the benefit of world-class facilities, attractions, shops and employment opportunities within walking distance of their front door as well as the wealth of excitement and opportunity in the city centre, just a short tram commute from nearby Holt Town Metrolink.

manchester mill an old spinning mill formally Victoria mill investment development

 

For further information please contact Flambard Williams: 

Head Office: +44 (0)20 7183 0646

Alternatively to speak directly to a specialist agent about Manchester Mill complete the form below.

 

Property Highlights

  • Stunning Grade II Listed Building
  • Returns of up to 10%
  • £1Billion Regeneration area
  • 2 Bed Apartments from £193k
  • High Spec Finish - Quartz Work Surfaces
  • Short Term Lets Allowed
  • 10 minute walk from Ancoats
manchester mill an old mill in the north west now a development

May 2022

UPDATE FROM ADMINISTRATORS

Practical Completion of the development is delayed due to two major items of work:

1. External drainage works;

Amended planning permission has been obtained for these works. Positively, it is no longer a requirement for these works to be completed prior to the development achieving Practical Completion, which means these works will not cause further delays to the completion of the individual units.

2. Firestopping works between the commercial ground floor and upper residential floors.

These works however, remain a very complex issue and the contractors are continuing to review options so that the most expeditious solution can be secured.

Consequently, the administrators not yet able to provide a definitive timeframe on when these works will be completed, and when final Building Control sign-off will be achieved.

With the above considered, the best estimate for Practical Completion is now Q4 2022/ Q1 2023.

More positively, the apartments and most common areas of the building are now substantially complete, with the snagging process ongoing.

The apartments will be available to view by appointment only in early July, exact date to be confirmed.

April 2022

Works to the apartments are now largely complete with the snagging process now drawing to a close. Works to the common parts remain ongoing with some final testing required following the installation of the water tank. Two attenuation tanks are required to be installed within the car parking areas which required a variation of planning. It is not anticipated however that this will delay practical completion and sign off. Listed Building Consent for the fire proofing works that are required between the basement, ground floor and first floor levels is still outstanding and for this reason we now anticipate a PC date of September 2022. Mortgage valuations can be booked for survey access in May 2022.

Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update
Spinning mill property development in manchester for buy to let investments - April construction update

March 2022

Works to the apartments are now largely complete with the snagging process now drawing to a close

Works to the common parts remain ongoing with some final testing required following the installation of the water tank. Two attenuation tanks are required to be installed within the car parking areas which required a variation of planning. It is not anticipated however that this will delay practical completion and sign off.

Listed Building Consent for the fire proofing works that are required between the basement, ground floor and first floor levels is still outstanding and for this reason we now anticipate a PC date of September 2022.

Mortgage valuations can be booked for survey access in May 2022.

February 2022

Works to individual apartments are now substantially complete and the snagging process has commenced.

Installation of the water tank is due to be completed imminently which will in turn allow for works within the communal areas to be brought to a close.

Building Control have identified that fire proofing is required within the basement and Ground Floor commercial areas and the First Floor residential areas. These works in turn will require further Listed Building Consents to be approved.

With the above considered it is estimated that Listed Building Control sign off will be Q3 2022.