Sold out!

Surrounded by greenfield spaces and river waterways yet close to Salford Quays and Manchester city centre

Situated on Ordsall Lane – one of Salford’s most emerging residential areas, the development is perfectly located – directly bordering Salford Quays and just a short walk away from Manchester’s thriving city centre.

Bridgewater Point is comprised of 220 residential units, made up of a mixture of stunning studio, 1, 2, and 3 bedroom apartments, as well as a selection of beautiful townhouses, spread over seven floors. All apartments are furnished using only the highest quality materials and appliances, and are decorated in a contemporary chic manner.

Furthermore, the development is home to a number of residential amenities to heighten the feel of luxurious living. A private on-site gym, secure bicycle storage and a beautifully landscaped communal garden area were purposefully designed with residents in mind, while the on-site management office is on-hand to ensure that each and every tenant is fully happy in their new home.

Property Highlights

  • Studio - 3 Beds
  • 1 - 2 Baths
  • 42 - 83 sq.m
  • Ordsall Lane
    Salford. M5 4TD
  • Sought After Location
  • Prime Rental Market
  • Great Transportation Links
  • Experienced Developers
  • Fully Managed Investment
  • 6% NET Assured Rental Yields

August 2018

Block A -

- Reception area complete , reception counter installed , minor decoration works to be completed

- Level 1 to 4 – complete with minor final snagging and cleaning being carried out

- Level 5 – Units are 95% compete with all kitchens and sanitaryware installed, M&E second fix completed, as well as 2nd fix joinery. Finishes trades closing out the final decorations and floor finishes, followed by final sparkle clean

- Corridors ceilings are all installed with decoration well progressed the floor coverings have begun to be installed through communal areas.

- Due for total completion – End of July, with final snagging and cleaning to follow.

Block B -

- Due for completion – Completions to begin Start of August.

- Floors 1-2 are 95% complete with floor coverings complete and programmed works for electrical testing to commence along with water tests.

- Floors 3-4 are 90% complete with floor coverings progressing and final stages of joinery works.

- Floors 5-6 are 85% M&E second fix works being carried out along with 2nd fix joinery. Decoration continuing throughout.

- Floors 7-8 are 75% complete with final kitchens been installed and remaining plots to be mist coated.

- Final Completion for Block B estimated – Mid September.

- The external podium works has steelwork, metal deck and concrete poured, Final brickwork to façade completing, waterproofing to deck progressing well with external blockwork to follow.

- The podium/carpark is due for completion beginning of september, which will also allow the release of the town houses at GF.

June 2018

The show unit is now complete.

Block A
- Reception area 95% complete , reception counter installed , minor decoration works to be completed
- Level 1 to 4 - Units are 99% complete with final snagging and cleaning being carried out
- Level 5 - Units are 85% compete with all kitchens and sanitary-ware installed
- M&E second fix to be completed, as well as 2nd fix joinery
- Corridors ceilings are all installed
- Decoration well progressed
- Floor coverings have begun to be installed through communal areas
- Due for total completion - Mid of July, with final snagging and cleaning to follow

Block B
- Due for completion - Completions to being mid-July
- Floors 1-2 are 90% complete with floor coverings complete
- Programmed works for electrical testing to commence along with water tests
- Floors 3-4 are 85% complete with floor coverings progressing and final stages of joinery works
- Floors 5-6 are 75% M&E second fix works being carried out along with 2nd fix joinery
- Decoration continuing throughout
- Floors 7-8 are 70% complete with final kitchens been installed and remaining plots to be mist coated
- Final Completion for Block B estimated - Mid August
- The external podium works has steelworks, metal deck and concrete poured, works to the external areas commencing
- The podium/car park is due for completion end of August, which will also allow the release of the townhouses at GF level

COMPLETION DUE Q3 2018

May 2018

Block A
- Reception area 85% complete
- Reception counter installed
- Post boxes installed
- Ceramic tiles to be installed week commencing 21/5/18
- Level 1 to 4 units are 95% complete with electrical testing and plumbing checks been made
- Level 5 units are 75% compete with kitchens been installed and mist coating been applied to all units
- Corridors ceilings are all installed with decoration well progressed the floor coverings will been done at later stages

Block B
- Floors 1-3 are 85% complete with floor coverings complete
- Programmed works for electrical testing to commence along with water tests
- Floors 3-6 are 75% complete with floor coverings progressing and final stages of joinery works
- Floors 7-8 are 65% complete with final kitchens been installed and remaining plots to be mist coated
- The external podium works is progressing with steel works been installed
- The podium/car-park is due for completion end of August

April 2018

March 2018

- The show unit is now complete

February 2018

January 2018

- The show unit is now ready for furniture installation
- External work is progressing well with both blocks becoming water tight
- The glass balustrade is now in place allowing the removal of scaffolding and mass climbers to Block A
- 1st fix works progressing to all floors with decorators mist coating units ready for joinery install
- Bathrooms have been tiled ready for final checks with water supply soon to be turned on

December 2017

October 2017

May 2017

FX Illustration

£
Approx.

Disclaimer
Rates are updated every 24hrs

Stamp Duty

£
Approx.
Next steps
Speak to one of our expert consultants today

Our customers

Not just a sale

I recall working through Flambard Williams to acquire my first property. Having met more real estate agents (over 50). I found them to follow up on everything. All concerns such as location, development company, solicitors, payment reminders were handled by them. They have local knowledge of the areas and are aware of the development and the surrounding. I do wish they also had a unit for London and other cities.

Asif
Great service

Friendly, helpful and professional staff. Very pleased with my purchase.

Jessica
Martyn Taylor and the team at Flambard Williams

Martyn Taylor provided consistently professional service, patience, and professionalism as we negotiated the purchase of an investment property from abroad. His knowledge and expertise are exemplary and I commend him, his colleagues, and the company for their courtesy.

Dr J Jacobs
Great customer experience!

Gave us a lot of information beforehand and kept us updated. Also assisted with any issues we had with solicitors and generally made the whole process smoother.

Polad
Flambard Williams are a team of honest & professional people

The consistency and quality of services provided by Flambard Williams are very good. They are efficient in responding, and provide best expertise available in their sector. You are always updated. So, you need not worry about futures. With Flambard, you have absolute advantage, in that you receive honest advice and hassle free service.

Mr M Mekhaimar

As featured in