Surrounded by greenfield spaces and river waterways yet close to the amenities of both Salford and Manchester

For sale exclusively with Flambard Williams is Apartment 509 Bridgewater Point…

A 1 bed property situated on the 5th floor of this brand new development adjacent to the River Irwell in Salford. Being conveniently located close to Manchester city centre and MediaCity makes this an attractive option for renters and buyers.

Situated on Ordsall Lane – one of Salford’s most emerging residential areas, the development is perfectly located – directly bordering Salford Quays and just a short walk away from Manchester’s thriving city centre.

Bridgewater Point is comprised of 220 residential units, made up of a mixture of stunning studio, 1, 2, and 3 bedroom apartments, as well as a selection of beautiful townhouses, spread over seven floors. All apartments are furnished using only the highest quality materials and appliances, and are decorated in a contemporary chic manner.

Furthermore, the development is home to a number of residential amenities to heighten the feel of luxurious living. A private on-site gym, secure bicycle storage and a beautifully landscaped communal garden area were purposefully designed with residents in mind, while the on-site management office is on-hand to ensure that each and every tenant is fully happy in their new home.

Property Highlights

  • 1 Bed
  • 1 Bath
  • 521 sq.ft
  • Ordsall Lane
    Salford. M5 4TD
  • Sought After Location
  • Prime Rental Market
  • Great Transport Links
  • Riverside Development
  • Fully Managed Investment
  • Bike Storage
  • On-Site Gym
  • Communal Gardens
  • 250 Year Leasehold
  • Assured Rental Yields

August 2018

Block A
- Reception area complete , reception counter installed , minor decoration works to be completed
- Level 1 to 4 - complete with minor final snagging and cleaning being carried out
- Level 5 - Units are 95% compete with all kitchens and sanitary-ware installed, M&E second fix completed, as well as 2nd fix joinery
- Finishes trades closing out the final decorations and floor finishes, followed by final sparkle clean
- Corridors ceilings are all installed with decoration well progressed
- Floor coverings have begun to be installed through communal areas
- Due for total completion - End of July, with final snagging and cleaning to follow

Block B
- Due for completion – Completions to begin Start of August
- Floors 1-2 are 95% complete with floor coverings complete
- Programmed works for electrical testing to commence along with water tests
- Floors 3-4 are 90% complete with floor coverings progressing and final stages of joinery works
- Floors 5-6 are 85% M&E second fix works being carried out along with 2nd fix joinery
- Decoration continuing throughout
- Floors 7-8 are 75% complete with final kitchens been installed and remaining plots to be mist coated
- Final Completion for Block B estimated - Mid September
- The external podium works has steel-work, metal deck and concrete poured
- Final brickwork to façade completing, waterproofing to deck progressing well with external blockwork to follow
- The podium/car park is due for completion beginning of September, which will also allow the release of the town houses at GF

June 2018

The show unit is now complete.

Block A
- Reception area 95% complete , reception counter installed , minor decoration works to be completed
- Level 1 to 4 - Units are 99% complete with final snagging and cleaning being carried out
- Level 5 - Units are 85% compete with all kitchens and sanitary-ware installed
- M&E second fix to be completed, as well as 2nd fix joinery
- Corridors ceilings are all installed
- Decoration well progressed
- Floor coverings have begun to be installed through communal areas
- Due for total completion - Mid of July, with final snagging and cleaning to follow

Block B
- Due for completion - Completions to being mid-July
- Floors 1-2 are 90% complete with floor coverings complete
- Programmed works for electrical testing to commence along with water tests
- Floors 3-4 are 85% complete with floor coverings progressing and final stages of joinery works
- Floors 5-6 are 75% M&E second fix works being carried out along with 2nd fix joinery
- Decoration continuing throughout
- Floors 7-8 are 70% complete with final kitchens been installed and remaining plots to be mist coated
- Final Completion for Block B estimated - Mid August
- The external podium works has steelworks, metal deck and concrete poured, works to the external areas commencing
- The podium/car park is due for completion end of August, which will also allow the release of the townhouses at GF level

COMPLETION DUE Q3 2018

May 2018

Block A
- Reception area 85% complete
- Reception counter installed
- Post boxes installed
- Ceramic tiles to be installed week commencing 21/5/18
- Level 1 to 4 units are 95% complete with electrical testing and plumbing checks been made
- Level 5 units are 75% compete with kitchens been installed and mist coating been applied to all units
- Corridors ceilings are all installed with decoration well progressed the floor coverings will been done at later stages

Block B
- Floors 1-3 are 85% complete with floor coverings complete
- Programmed works for electrical testing to commence along with water tests
- Floors 3-6 are 75% complete with floor coverings progressing and final stages of joinery works
- Floors 7-8 are 65% complete with final kitchens been installed and remaining plots to be mist coated
- The external podium works is progressing with steel works been installed
- The podium/car-park is due for completion end of August

April 2018

March 2018

- The show unit is now complete

February 2018

January 2018

- The show unit is now ready for furniture installation
- External work is progressing well with both blocks becoming water tight
- The glass balustrade is now in place allowing the removal of scaffolding and mass climbers to Block A
- 1st fix works progressing to all floors with decorators mist coating units ready for joinery install
- Bathrooms have been tiled ready for final checks with water supply soon to be turned on

December 2017

October 2017

May 2017

Property enquiry

FX Illustration

£
Approx.

Disclaimer
Rates are updated every 24hrs

Stamp Duty

£
Approx.

Latest news and publications

Our customers

A very impressive company

I can’t really praise the service I’ve received highly enough. Personal, professional and very efficient. Charleigh has been with me the whole way and I can’t thank her enough. I would recommend this company to anyone!

Mr J Wild
Great service

Friendly, helpful and professional staff. Very pleased with my purchase.

Jessica
Friendly and Pro-active

In my dealings with them I found Flambard Williams helpful, friendly and pro-active.

Mr D Jones

Proud to be featured in