Art Apartments
The Perfect Synergy of Classic Styling
Art Apartments
Art Apartments in Liverpool is the perfect synergy of classic styling with exceptional specification. This development has modern apartments ranging from 1-2 bedrooms which also has balconies with stunning views.
Why Invest in Art Apartments?
There seems little doubt that with so much local investment aimed at boosting high value, high skill industries, Liverpool will see a steady escalation in demand for top quality
accommodation aimed at the discerning professional market. Recognising this, the ART Apartments scheme is seeking to create some of the most desirable new properties in the city. For residents, it will provide luxurious city centre lodgings, while for investors, it promises ready demand and easy affordability.
Art Apartments Location
Art Apartments convenient location is just 500m from the city centre.
For further information please contact Flambard Williams:
Head Office: +44 (0)20 7183 0646
Alternatively to speak directly to a specialist agent about Art Apartments complete the form below.
Property Highlights
- 1 - 2 Beds
- 1 Bath
- Tabley Street, Liverpool, Merseyside. L1 8DX.
500m from City Centre
Stunning Balcony Views
High Demand Area
2 Lifts
Car Parking
December 2020
Prior to the domestic delays experienced by Ridgemere Limited, in particular relating to the SFS framing design which formed a critical path activity, the Works on site were progressing well in line with the resequencing programme issued by Ridgemere Limited. Unfortunately the further steel sub-contractor issues and Covid-19 Pandemic have additional delays on site, with continued industry enforced restrictions.
Substructure works, including piling and foundations, are complete with the brick / blockwork to the ground floor areas now complete ready for services connections and plant.
Tower A' structure is complete with SFS framing installed, weatherboarding and external windows installation complete to three elevations with blockwork nearing completion to the fourth elevation. Internal partition studwork is also complete on all floors with plasterboard to one side and first fix M&E ongoing, currently at fourth to sixth floor. The flat roof finishes are also complete with the pitched roof to commence after the Christmas shutdown , with façade brickwork continuing to all elevations.
'Tower B' and 'Tower C' both have the steel frame complete with upper floor deck and concrete complete to all floors and the roof. Tower B/C' has progressed significantly so that the works are now at a similar floor level across the entire project. The lift shaft blockwork is complete, ready for the lift to be installed in early 2021. Below ground drainage, including attenuation and the hydrobrake, are complete with only the mains connection required. The connection works are currently being scheduled with the relevant paperwork for the required road closure, street works and connection approval in process.
In the last month, Ridgemere Limited's progress has reduced due to limited operatives on site as a result of ongoing Covid-19 control measures related to the increased testing regime recently introduced in the Liverpool City Region. Ridgemere Limited have agreed to provide a show apartment for purchaser / tenant viewing and to provide a quality benchmark for the scheme. The location and date for provision of the show apartment is still to be confirmed by Ridgemere Limited.
October 2020
Tower A structure is complete with SFS framing installed, weatherboarding and external windows installation complete to three elevations with blockwork ongoing to the remaining elevation. Internal partition studwork is also complete on all floors with plasterboard to one side and first fix M&E ongoing. The flat roof finishes are also complete with the exception of parapet capping awaiting brickwork completion, with facade brickwork ongoing to all elevations.
Tower B and Tower C both have the steel frame complete with upper floor deck and concrete complete to all floors and the roof.
August 2020
Ridgemere Limited have confirmed orders for both electrical and water mains supplies have been placed and accepted by Scottish Power and United Utilities respectively.
At Site Progress Meeting on 04-Feb-20, Ridgemere Limited advised that due to a number of historic issues with domestic sub-contractors, and termination / replacement of said sub-contractors, the works had been delayed by circa 4 months from Nov-19 to Mar-20.
This was subsequently further impacted by delays experienced by the steel fabricator / erector due to sub-contractor cash flow restrictions, however this had been overcome and the frame complete prior to the meeting.
However this further delay had deferred the completion date to the end of Jul-20. Subsequently, due to the impact of the Covid-19 Pandemic on the construction industry, the project has incurred further delays since Mar-20 with the ongoing restrictions placed on construction activities by the UK Government and Construction Leadership Councils' 'Site Operating Procedures' ("SOPs") the project is anticipated to incur an extended period of inefficiency; this currently ranges from 13% to 60+% across the industry. On this basis a further programme has been issued by Ridgemere Limited anticipating completion of the project before Christmas 2020.
FX Illustration
Disclaimer
Rates are updated every 24hrs