Sold out!

Stunning Development Exclusive to Flambard Williams

Exclusive to Flambard Williams is this re-sale in one of Salford’s newly built and most stylish developments – Adelphi Wharf Phase One.

Apartment No. 504 is a stunning 2 Bed, 2 Bath property, situated on the 5th Floor of this beautiful, brand new development. Located on the banks of the River Irwell, this is the ideal investment as the apartment is currently built and tenanted.

The attractive setting with views stretching across the River Irwell puts Adelphi Wharf at the top of the list when buying in Greater Manchester. Situated in ideal position between Salford and Manchester equates to not only a fantastic residential development but one which has extremely high rental potential.

Fortis Developments have a proven track record of developing fantastic high-spec apartments throughout the UK and Adelphi Wharf is no exception. Featuring Large terraces, stunning gardens and stunning apartments, this development has something for everyone.

Investors benefit from a development which already has an extremely high occupancy rate and residents will be living in what is one of the most sought after developments in the area.

Purchasing this apartment at Adelphi Wharf could not be easier. Flambard Williams proficient staff will walk you through the process from start to finish.

For further information please contact Flambard Williams: 

Head Office: +44 (0)20 7183 0646

Alternatively to speak directly to a specialist agent about Adelphi Wharf please complete the form below.

Property Highlights

  • 2 Beds
  • 2 Baths
  • 699 sq.ft
  • Adelphi Street
    Salford. M3 6EN
  • Award Winning Development
  • Waterfront Property
  • Ideal Location
  • Prime Rental Market
  • Great Transport Links
  • On-Site Gym
  • Bike Storage
  • 250 Year Leasehold
  • Circa 6% NET Rental Yields
  • Fully Managed

May 2021

April 2021

February 2021

November 2020

October 2020

September 2020

May 2020

April 2020

March 2020

February 2020

December 2019

October 2019

July 2019

May 2019

- Groundworks are well underway
- Full hoarding and site offices have been installed onsite
- Piling and wider groundworks are being carried out

March 2019

Block A
- Lower Ground – Rooms 70% completed, final plumbing works underway
- Ground Floor – Rooms 95% completed, currently de-snagging
- Levels 3 to 5 – Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 - Rooms 80% completed, snagging underway
- Level 8 – Rooms 70% completed, final plumbing works underway
- Level 9 – Rooms 70% completed, final plumbing works underway

Block B
- Lower Ground – Rooms 70% completed, final plumbing works underway
- Ground Floor – Rooms 95% completed, currently de-snagging
- Levels 3 to 5 – Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 - Rooms 80% completed, snagging underway
- Level 8 – Rooms 70% completed, final plumbing works underway

Block C
- Townhouses – Rooms 60% completed, final electrical works underway
- Lower Ground – Rooms 97% completed, flooring to be laid
- Ground Floor – Rooms 97% completed, flooring to be laid
- Levels 3 to 4 - Rooms 97% completed, flooring to be laid
- Level 5 – Rooms 80% completed, snagging underway
- Level 6 – Rooms 70% completed, final plumbing works underway

- Cladding to Block C – 100% completed
- Brickwork to block A & B 95% completed
- Groundworks complete to the perimeter of Block C allowing hard landscaping to begin

August 2018

PHASE 1

Block A
- Lower Ground – Rooms 50% completed, first coat decoration underway.
- Ground Floor – Rooms 95% completed, currently de-snagging
- Levels 3 to 5 – Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 – Rooms 70% completed, final plumbing works underway
- Level 8 – Rooms 50% completed, final electrical works underway
- Level 9 – Rooms 50% completed, final electrical works underway

Block B
- Lower Ground – Rooms 70% completed, final plumbing underway
- Ground Floor - Rooms 95% completed, currently de-snagging
- Levels 3 to 5 - Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 – Rooms 70% completed, final plumbing works underway
- Level 8 -Rooms 50% completed, final electrical works underway

Block C
- Townhouses – Rooms 60% completed, final electrical works underway
- Lower Ground – Rooms 95% completed, flooring to be laid
- Ground Floor – Rooms 95% completed, flooring to be laid
- Levels 3 to 4 - Rooms 95% completed, flooring to be laid
- Level 5 – Rooms 80% completed, snagging underway
- Level 6 – Rooms 50% completed, final electrical works underway

Externals
- Cladding to block C – 95% completed
- Brickwork to block A & B 95% completed
- Groundworks will allow safe access into the building are underway starting at block C working towards block B & A

May 2018

PHASE 1

Block A
- Lower Ground - Rooms 40% completed, first coat decoration underway
- Ground Floor - Rooms 90% completed, currently de-snagging
- Levels 3 to 5 - Rooms 90% completed, currently de-snagging
- Level 6 - Rooms 70% completed, final plumbing works underway
- Level 7 - Rooms 60% completed, Kitchen install and tiling underway
- Level 8 - Rooms 30% completed, plastering underway
- Level 9 - Rooms 30% completed, plastering underway

Block B
- Lower Ground - Rooms 60% completed, final plumbing underway
- Ground Floor - Rooms 90% completed, currently de-snagging
- Levels 3 to 5 - Rooms 80% completed, snagging underway
- Level 6 - Rooms 70% completed, final plumbing works underway
- Level 7 - Rooms 60% completed, kitchen install and tiling underway
- Level 8 - Rooms 30% completed, plastering underway

Block C
- Townhouses - Rooms 50% completed, final electrical works underway
- Lower Ground - Rooms 95% completed, flooring to be laid
- Ground Floor - Rooms 95% completed, flooring to be laid
- Levels 3 to 4 - Rooms 90% completed, currently de-snagging
- Level 5 - Rooms 70% completed, final plumbing works underway
- Level 6 - Rooms 20% completed, initial electrical works underway

Externals
- Cladding to block C - 95% completed
- Brickwork to block A & B - 95% completed
- Groundworks that will allow safe access into the building are underway starting at block C working towards block B & A

PHASE 3
- Building foundations have commenced followed by the main concrete frame for the blocks

April 2018

March 2018

February 2018

January 2018

PHASE 1

Block C
- All kitchens up to level 5 are now fitted
- Joinery is progressing well, also up to level 5
- Tiling following through, currently up to level 3
- The top floor partition works are being completed, ready for plastering
- Envelope final stages are being completed, the roofing is also fully installed

Block A / Block B
- Decorating is progressing well, working bottom up, currently up to the 2nd floor
- Sanitary ware is being fitted on the 3rd floor along with 2nd fix joinery
- Window frame 90% installed, external insulation and brick work also progressing

PHASE 2 & 3

- Building foundations have commenced followed by the main concrete frame for the blocks

October 2017