Sold out!

A contrast of city and country living that provides a residential retreat

Adelphi Wharf is in the heart of an area galvanised by both a rising population and regeneration, but its countryside appeal is not lost thanks to endless views of the river and meadows.

This award winning development will be a beautiful tenant retreat, providing peaceful landscaped gardens alongside modern urban living. Residents will overlook the River Irwell as well as living within easy reach of Manchester’s city centre.

Each apartment will be furnished to the highest standard. In addition, residents of Adelphi Wharf will have access to a state-of-the-art private on-site gymnasium in Phase 1 of the development, as well as communal areas and secure bike storage for all residents and allocated parking spaces for selected units.

Property Highlights

  • Studio - 3 Beds
  • 1 - 2 Baths
  • 36 - 114 sq.m
  • Adelphi Street
    Salford. M3 6EN
  • Award Winning Development
  • Waterfront Property
  • Ideal Location
  • Prime Rental Market
  • Great Transport Links
  • 250 Year Leasehold
  • Completion Due Q1 2018
  • Circa 6% NET Rental Yields
  • Fully Managed

August 2018

Phase 1

Block A -

Due for completion – Early August

Lower Ground – Rooms 50% completed, first coat decoration underway.
- Ground Floor – Rooms 95% completed, currently de-snagging
- Levels 3 to 5 – Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 – Rooms 70% completed, final plumbing works underway
- Level 8 – Rooms 50% completed, final electrical works underway
- Level 9 – Rooms 50% completed, final electrical works underway

Block B -

Due for completion – Early August

- Lower Ground – Rooms 70% completed, final plumbing underway
- Ground Floor - Rooms 95% completed, currently de-snagging
- Levels 3 to 5 - Rooms 95% completed, currently de-snagging
- Level 6 - Rooms 80% completed, snagging underway
- Level 7 – Rooms 70% completed, final plumbing works underway
- Level 8 -Rooms 50% completed, final electrical works underway

Block C -

Due for completion – Late July

- Townhouses – Rooms 60% completed, final electrical works underway
- Lower Ground – Rooms 95% completed, flooring to be laid
- Ground Floor – Rooms 95% completed, flooring to be laid
- Levels 3 to 4 - Rooms 95% completed, flooring to be laid
- Level 5 – Rooms 80% completed, snagging underway
- Level 6 – Rooms 50% completed, final electrical works underway

Externals -

- Cladding to block C – 95% completed
- Brickwork to block A & B 95% completed
- Groundworks will allow safe access into the building are underway starting at block C working towards block B & A

May 2018

PHASE 1&2

Block A
- Due for completion - Last week in July
- Lower Ground - Rooms 40% completed, first coat decoration underway
- Ground Floor - Rooms 90% completed, currently de-snagging
- Levels 3 to 5 - Rooms 90% completed, currently de-snagging
- Level 6 - Rooms 70% completed, final plumbing works underway
- Level 7 - Rooms 60% completed, Kitchen install and tiling underway
- Level 8 - Rooms 30% completed, plastering underway
- Level 9 - Rooms 30% completed, plastering underway

Block B
- Due for completion - Last week in June
- Lower Ground - Rooms 60% completed, final plumbing underway
- Ground Floor - Rooms 90% completed, currently de-snagging
- Levels 3 to 5 - Rooms 80% completed, snagging underway
- Level 6 - Rooms 70% completed, final plumbing works underway
- Level 7 - Rooms 60% completed, kitchen install and tiling underway
- Level 8 - Rooms 30% completed, plastering underway

Block C
- Due for completion - Last week in June
- Townhouses - Rooms 50% completed, final electrical works underway
- Lower Ground - Rooms 95% completed, flooring to be laid
- Ground Floor - Rooms 95% completed, flooring to be laid
- Levels 3 to 4 - Rooms 90% completed, currently de-snagging
- Level 5 - Rooms 70% completed, final plumbing works underway
- Level 6 - Rooms 20% completed, initial electrical works underway

Externals
- Cladding to block C - 95% completed
- Brickwork to block A & B - 95% completed
- Groundworks that will allow safe access into the building are underway starting at block C working towards block B & A

PHASE 3

- Building foundations have commenced followed by the main concrete frame for the blocks

April 2018

March 2018

February 2018

January 2018

PHASE 1

Block C
- All kitchens up to level 5 are now fitted
- Joinery is progressing well, also up to level 5
- Tiling following through, currently up to level 3
- The top floor partition works are being completed, ready for plastering
- Envelope final stages are being completed, the roofing is also fully installed

Block A / Block B
- Decorating is progressing well, working bottom up, currently up to the 2nd floor
- Sanitary ware is being fitted on the 3rd floor along with 2nd fix joinery
- Window frame 90% installed, external insulation and brick work also progressing

PHASE 2 & 3

- Building foundations have commenced followed by the main concrete frame for the blocks

October 2017

FX Illustration

£
Approx.

Disclaimer
Rates are updated every 24hrs

Stamp Duty

£
Approx.
Next steps
Speak to one of our expert consultants today

Our customers

Good communication & regular feedback

I am pleased with my relationship with FW. Communication 4000 miles away and different time zone and weekend holidays was very effective and personal.

Mr Husain
Flambard Williams are a team of honest & professional people

The consistency and quality of services provided by Flambard Williams are very good. They are efficient in responding, and provide best expertise available in their sector. You are always updated. So, you need not worry about futures. With Flambard, you have absolute advantage, in that you receive honest advice and hassle free service.

Mr M Mekhaimar
Friendly and Pro-active

In my dealings with them I found Flambard Williams helpful, friendly and pro-active.

Mr D Jones
Great customer experience!

Gave us a lot of information beforehand and kept us updated. Also assisted with any issues we had with solicitors and generally made the whole process smoother.

Polad
Not just a sale

I recall working through Flambard Williams to acquire my first property. Having met more real estate agents (over 50). I found them to follow up on everything. All concerns such as location, development company, solicitors, payment reminders were handled by them. They have local knowledge of the areas and are aware of the development and the surrounding. I do wish they also had a unit for London and other cities.

Asif

As featured in